The initial remit involved the construction of the pre earthworks drainage, environmental outfalls, welfare establishments and site accesses.
The Site Management soon recognized that our can do attitude could help them resolve some of the more problematic elements of the construction. Soon we were awarded the package of works to construct the Environmental Swales, Attenuation Ponds and Lagoons, working in areas of Sites of Scientific Interest and to assist in the construction of the highest reinforced earth highway embankment. From there the relationship blossomed and we were awarded the remaining 5km of highway drainage, the Accommodation Works and the Completion Works.
Client:
Alfred McAlpine
Location:
A30 Bodmin, Cornwall
Value
1.6 Million